HOW TO ENSURE YOU GET PAID FOR VARIATIONS (1)

Getting paid for variations is the holy grail of specialist contracting and is the most common battleground for payment disputes. But unfortunately, the ‘how to ensure you get paid for variations’ eludes many specialist contractors.

IF you’re one of the many who drive an Audi, then you may be interested to know the car manufacturer has recently won an advertising industry Gold Award for increasing the desirability of the new Audi R8.

When I read things like this, I always want to find out what they had to do to win, and what I can learn from it. More importantly, what you can learn from it.

WHAT is a variation?

A variation can manifest itself as an addition to, or reduction in, or change to the scope of work under the contract, or the conditions under which the work is to be carried out.

The effect of variations in construction sub-contracts
Variations need to be carefully assessed in terms of: impact on the programme or time for completion, rate of progress of the work, and last but not least changes to the cost.

It’s common for specialist contractors to fail to properly consider and indeed administer these issues correctly. The net result is that they don’t get paid properly, or they incur costs they can’t recover, or they get clobbered for delays. Sometimes all three!

Are sub-contractors obliged to carry out variations?

In addition to setting out all sorts of other provisions including your scope of work, most contracts will normally provide terms for the administration of variations. If there are no terms and conditions, then getting paid for variations will be so much harder, and you might want to get some professional advice from the outset. You could put your own terms in place for instance.

So, yes ordinarily you do have to undertake variations, but whatever you do, you must ensure you don’t carry out variations unless those variations have been properly instructed in accordance with the terms of the contract.

Instructions are essential if you want to get paid
Now we all know that some Contractors will get annoyed if you insist on proper instructions. But please understand this. The contracts manager who wants you to get the job done, has probably got no say whatsoever when it comes to you actually getting paid.

Indeed, the first thing the QS (whose job it is to pay as little as possible) will say is; ‘where’s your instruction?’ This will be swiftly followed by: ‘I’m not paying for anything you’ve done without instructions.’

So, don’t allow anyone to bully you into doing additional work without proper instructions. Because the simple fact of the matter is that you won’t get paid.

You need to be careful about this, and you must understand what your contract says, because you need to ensure you and the contractor are following the correct contractual procedure.

Can I agree the price in advance?

Ordinarily the answer to this question is sadly no.

The reasons for this are historical, and beyond the scope of this article, but suffice to say; most contracts are written on the basis that you get an instruction, you do the work, and then it gets valued.

Of course, you can agree a set of terms that do provide for agree first action later, and the NEC/3 or NEC/4 as it is now, are drawn up on that basis. But the key thing is to understand exactly what the rules say!

Most contracts will describe the process under which a variation may be requested, accepted, and approved. You should read up on this and make sure both you and the contractor stick to it.

That’s because not following the contract’s proper procedures, is a sure-fire way to not get paid. So, if the contractor is bullying you to do work without following the procedure, then I suggest you get our professional advice.

His attitude is unlikely to get better, and you are almost certainly heading for valuation and payment problems.  

Procedures relating to variations
All variations need to end up on paper. In other words, they need to be properly recorded! As mentioned above the contract will describe what documents and procedures are required for a valid variation to be approved under the contract. So, know what they are and follow them.

If your contract is less formal and there is no specified procedure, then get the request and approval on paper. This can be documented on your own Site Instruction Form, Site Diary, an email exchange, or even your own ‘Confirmation of Verbal Instruction’ form.

This kind of document can become valid contemporaneous evidence that additional work was requested and to which you agreed to carry out.

Claim for variations every month
One of the biggest mistakes made by many specialist contractors is holding off on claiming variations until the later stages of the job.
If you don’t make a claim for it, then don’t be surprised if the contractor has conveniently forgotten just how much additional work was carried out. And the shock of the additional cost might well express itself in anger and non-payment.

The longer you go without documenting all the additional work, the greater the likelihood the details will get forgotten, and the harder it will be to get paid.

So, the lesson here is to claim for variations every single month in your normal monthly progress claim. Don’t be shy, and don’t dither. Do it.

If you’re going to have a disagreement with the contractor, then do it early rather than at the end of the job when you’ve incurred the cost of all the additional work but have not been paid for any of it.

Getting paid for variations requires strength and discipline
Getting paid for variations requires the strength to press your case against the contractor, and the discipline to keep excellent documentation. But once you’ve done it once, it will get easier. You will get stronger and better at the paperwork, and better at knowing how to follow the contract’s requirements.

As specialist contracting is all about entering into legally binding commercial contracts (with contractors or clients) that require you to undertake variations, you will be pleased to know that you can access a wealth of information on Streetwisesubbie.com to answer your questions about how to get paid for construction variations and the valuation of and payment for variations in construction and engineering sub-contracts.
And as always please feel free to call us if you have a problem.
01773 712116
info@streetwisesubbie.com
www.streetwisesubbie.com