Understanding flooring terminology is essential for achieving a quality finish, says Adam Jones. From walk-on times to curing, knowing what product timings mean helps prevent costly mistakes and callbacks
THE start of a new year often brings new people onto site. Apprentices settling into their first full season, fitters moving across from other trades, site managers who need flooring timings explained before they programme the next phase. It’s also a good moment for experienced installers to check that the words printed on a tub or a data sheet still mean what they think they mean.
Flooring has a vocabulary of its own. Manufacturers use these terms on packaging and in technical documents because each one describes something specific about how a product behaves. Misread one and the consequences tend to show up later, in the finished floor. Below are some of the terms that come up most often, what they mean in practice, and what goes wrong when they’re misunderstood.
Walk-on time
This one usually applies to smoothing compounds. Walk-on time is the point at which the applied compound has dried enough to take foot traffic. Step on it any sooner and you’ll leave indentations. Those marks spoil the surface you’ve just laid, and they can show through whatever floorcovering goes down on top.
Airing time and trapped moisture
Airing time belongs to adhesives. It’s how long you wait after spreading the adhesive before placing the floor covering. During that period, moisture in the adhesive escapes into the air as vapour, so less of it is held in the adhesive when the covering goes down.
Shorten the airing time and that vapour still has to go somewhere. With the covering in place, it collects underneath and forms bubbles, one of the more common routes to blistering and bubbling in floorcoverings.
Open time
Once airing time has passed, open time begins. This is the period during which the adhesive will readily accept the floor covering, and laying within it gives you the best bond strength the product can achieve.
When open time runs out, the adhesive becomes less receptive quickly. Bond strength keeps falling from that point until the adhesive won’t bond at all.
Late placement
Late placement describes laying flooring into adhesive that has been left too long. The covering goes down, but the bond is badly weakened or missing entirely.
Without that bond holding it, the flooring moves with the conditions in the room. Resilient flooring is especially prone to this. As it expands and contracts, gaps can open between pieces, or the material can grow and push itself away from the substrate or against the flooring next to it.
Drying and curing
Both terms describe a product changing from a liquid to a solid, and both tell you when the next stage of work can follow. The difference lies in how that change happens.
Drying is the loss of the liquid components from the applied product. Some evaporates into the air and some is absorbed into the base the product sits on. Smoothing compounds and acrylic adhesives dry, because they rely on losing that liquid to reach their finished state.
Curing is a chemical reaction. Epoxy and polyurethane products cure, and they’re supplied as two components, normally marked Part A and Part B. Mixing the two starts a reaction inside the product that turns it from liquid to solid.
Data sheet timings assume test conditions
Every timing above comes from extensive testing by the manufacturer. That testing is carried out under standardised conditions, typically 20°C and 65% relative humidity (RH). When the site doesn’t match those conditions, the product won’t behave exactly as stated either.
In colder or damper conditions, expect timings to stretch. An adhesive with a stated airing time of 10 minutes could need 20, 30, 60 minutes or longer, and the colder and damper the site, the longer it gets.
Warm, dry conditions push things the other way. That 10-minute airing time might drop to five. The bigger concern is open time, which can shrink dramatically. 60 minutes on the data sheet can become 10 or 20 onsite, sometimes less. That leaves far less room before late placement becomes a risk, which is why applying adhesives in varying site conditions calls for regular checks of the adhesive rather than reliance on the clock.
Where the numbers live
You’ll find these timings in a product’s technical data sheet (TDS) and safety data sheet (SDS). Most manufacturers publish a TDS for each product. An SDS is a legal requirement for any product with a potentially hazardous or chemical component.
A TDS sets out what a product is and how it performs, so you can see what it does and where it should be used. It often covers how to apply it, what its limitations are, and how it fits into a system alongside other products. The two documents usually go together.
An SDS lists the product’s chemical components and any special requirements for handling it safely. It covers safe handling and working procedures, with information on physical data, toxicity, health effects and first aid. You’ll also find details of reactivity, transport, storage and disposal, along with protective equipment and what to do in the event of a spill.
Both are normally available on the manufacturer’s website. Bostik has a searchable database of data sheets, and you’ll also find them on individual product pages and in the Bostik Pro Floor app. If a manufacturer hasn’t put a TDS or SDS online, contact them for a copy. A TDS may not exist for every product, but manufacturers should supply an SDS on request.
If in doubt, ask
There are plenty more terms we could have covered, but these are the ones that cause the most confusion onsite. The simplest way to understand any of them is to ask. Technical teams answer these questions all the time, and the explanation is nearly always simpler than people expect. Getting the language right in January costs far less than a callback in February.