As part of their on-going commitment to produce much needed Covid-19 test kits; Randox Laboratories Ltd invested in a new facility at its existing headquarters in Crumlin, Co Antrim.


The specialised laboratory, the development of which was fast-tracked over the space of four weeks, is the first step in a wider diagnostics investment programme from the company.


Given the tight construction programme; Cemfloor were contacted and asked to propose a solution for the project.


Cemfloor CT C30F6 was specified and over a period of just 2 – days; 3800m2 was installed by O’Neill Concrete Flooring Ltd with the screed being supplied by Robinson Concrete Ltd.


Due to the high early strength of Cemfloor C30; the screed was loaded with access lifts 3 – days after installation which ensured that the build programme was able to continue with minimal disruption.


A liquid surface DPM was used to allow the vinyl flooring be installed onto the screed only 7 – days after installation.


Due to the incredible amount of effort by all parties involved; the entire project finished ahead of schedule with no issues.